Worked 40 hours
I focused this week on the Data Center Consolidation project. We having been doing upgrades to our network in order for it to be ready for clients to connect too. Honestly, my biggest part has been leading meetings in the middle of the night.
There has been good progression on all activities, but nothing much for me to do other than listen and then update the project plan.